 Heat Quantity Meter

The following step-by-step instructions will guide you through successful installation of the EESIFLO 6000 Series in the Heat Quantity Measurement mode, where a single flow transducer and two PT100 Temperature Sensors are employed to monitor the efficiency of HVAC and Chiller applications.

In cases where the temperatures of the inflow and/or the outflow are known, or are constant, you may enter these fixed temperatures manually. In this situation, the temperature sensors need not be connected, but the following instructions should still be followed, ignoring steps detailing installation of the temperature sensors.

For detailed instructions, please refer to the appropriate pages of the EESIFLO 6000 Series Operating Instructions

 

 Locate and Plug in the Sensors

In the following steps we will locate and install a single flow transducer and two temperature sensors.

  1. Locate the appropriate Transducer Pair (S2X, Q3X or M2X), and two PT100 Temperature Sensors.
  2. Plug the appropriate Flow Transducer Pair into the receptacle marked Channel A on the front of the EESIFLO 6000 Series.
  3. Plug the WHITE wired INLET Temperature Sensor into the receptacle marked T1 - Inlet on the rear of the EESIFLO 6000 Series. Note this is a screw-in connector.
  4. Plug the Black wired OUTLET Temperature Sensor into the receptacle marked T2 - Outlet on the rear of theEESIFLO 6000 Series Note this is a screw-in connector.
  5. Turn the EESIFLO 6000 Series ON by pressing the "On-C" button.
  6. TheEESIFLO 6000 Series will automatically detect which Flow Transducer Pair is installed, and display that information during boot-up.
 Setting up the Flow Transducers

In the following steps, we will define the pipe size, material, thickness, roughness, medium type and temperature

  1. Using the 4 or 6 keys, scroll the menu to PAR (parameters), then press ENTER.
  2. Press ENTER again to view Channel A Parameters
  3. Enter the Outer Pipe Diameter then press ENTER
  4. Enter Wall Thickness then press ENTER
  5. Using the 2 and 8 keys, scroll up or down through the available list and enter Pipe Material.
  6. Answer YES or NO to the prompt for Lining then press ENTER
  7. If NO Lining, jump to step 16
  8. Enter the Lining Type using the 2 and 8 keys to scroll up and down through the available list.
  9. Enter the Lining Thickness
  10. Enter the internal Roughness of the pipe then press ENTER
  11. Using the 2 and 8 keys to scroll up and down through the available list, enter the Medium (Liquid Type).
  12. Enter Medium Temperature. Note this is only a ROUGH estimate of the medium temperature.
  13. The menu screen will return to the main menu.